9. LIFE CYCLE STATES AND REVISIONS
9.1 Life Cycle States
The following table defines the Life Cycle States which shall be applied to documents
generated or obtained for the project. Each Life Cycle State has a single code
associated with it, which is used as part of the Revision. The use of the Life Cycle
State code as part of the Revision is explained in the following sections.

CONTRACTOR shall only assign Life Cycle State codes from Phase 3 (FEED) until
such time as the Project officially enters phase 4 (detailed design). Contractor shall
issue all Documents to COMPANY at the first life cycle after Interdisciplinary Review
in the applicable phase of the project, and each time the Document is revised
thereafter. CONTRACTOR may be required to submit a copy of Documents to
COMPANY at the time it is issued for interdisciplinary check as needed or the
Agreement requires.

9.2 Progression through Life Cycle States<

终于翻完了,难度很高。虽然所涉及的专业不熟悉,但语法关系搞清楚了,所以,如果有什么术语用得欠妥的话,提问者稍作改正即可。
9. LIFE CYCLE STATES AND REVISIONS
9.生命周期状态和修改
9.1 Life Cycle States
9.1生命周期状态
The following table defines the Life Cycle States which shall be applied to documents generated or obtained for the project. 下表定义了将被用于为项目所产生或获得的文件的生命周期状态。Each Life Cycle State has a single code associated with it, which is used as part of the Revision. 每个生命周期状态都有一个与其相关的单一代码,它就用作修改的一部分。The use of the Life Cycle State code as part of the Revision is explained in the following sections.如何将生命周期状态代码作为修改的一部分加以采用,在以下小节中加以说明。
CONTRACTOR shall only assign Life Cycle State codes from Phase 3 (FEED) until
such time as the Project officially enters phase 4 (detailed design).
(合同)承包者只应从第三阶段(进入阶段)起直至项目正式进入第四阶段(详细设计)为止,指定生命周期状态代码。Contractor shall issue all Documents to COMPANY at the first life cycle after Interdisciplinary Review
in the applicable phase of the project, and each time the Document is revised