2.保留合同第二部分通用条件第13.7款【因法律改变的调整】为和13.8款【因成本改变的调整】的内容。由于法律以及成本发生改变是不可以预见的,删除此项内容,风险全部转嫁于承包商;另外,我方坚持保留此两项条款也是考虑到更加科学、合理的报价。本项目合同工期为七年,在此长周期无保障的情况下,必将导致承包商考虑更多的风险因素而最终影响报价。
no
1. Engineers candidates and their replacement by the employer and the contractor jointly decided and selected, the employer can engineer qualification, work experience is limited. Side to adhere to this principle is based on three considerations: First, advocates of this clause is similar projects, the actual operation of the practice, rather than the company first; secondly, our loans to assist employers in China, handling matters relating to the project, our company the role played by more than a simple sense of the contractor; again, throughout the project design has not completely ended, the construction specifications of the trilateral project has yet to be refined, the full implementation of the project engineers, selected by the employer is not conducive to project development,
Is also unfair. Therefore, our engineers adhere to the selection and replacement shall be a mutual decision and selected.
2. To retain the second part of the contract, paragraph 【Gen